You need to Know the following:-
1 - The dependency relationships (SS,FS,SF,FF)
2 - Critical Path calculations.
3 - You need to study well the following :-
- communication Knowledge area. (PMBOK)
- Earned value
- Time Management knowledge area (PMBOK)
o Estimation Techniques and the difference between them
o Resource levelling , Fast track , Crashing techniques
o What-if scenario , Risk , Simulation
- The relation between risk , cost and schedule.
- Integrated change control
My advice to you is to study these Knowledge areas and enter the exam.
2 comments:
Thank you for your advice. There is a complementry guide called "Practice Standard for Scheduling", from PMI. I hope this should also be read apart from the knowledge areas you mentioned from PMBOK guide.
- Kaide Johar Manasi PMP
Yes sure you have to read it as well , I forgot to write it.
Thanks
Post a Comment